How a bored pile is made
Drill, reinforce, concrete: the sequence is told in three steps. What matters along the way and where a drill motor on an excavator comes in.
Verfahren
Methods
Pile foundation
Special civil engineering

KURZ GESAGT
A bored pile is made in three steps: first a hole is drilled into the ground, then a steel reinforcement cage is lowered in, finally the hole is filled with concrete. The rules for this are set out in EN 1536.
Häufige Fragen
Which standard applies to bored piles?
EN 1536 governs the execution of bored piles.
What is the difference between a bored pile and a micropile?
The diameter and with it the load-bearing capacity. Micropiles are slimmer, are therefore set in greater numbers and reach places a large rig cannot.
Can piles be installed under a railway overhead line?
Yes, with a method that works without a mast. A drill motor on an excavator only needs the height of the drive and the tool.
Sie sind unsicher, welches Modell passt?
Nennen Sie uns Ihr Trägergerät, wir empfehlen den passenden Antrieb.
PASSENDE MODELLE
Welcher Antrieb passt zu Ihrem Bagger?
Nennen Sie uns Gerät, Öldruck und Ölmenge. Wir legen den Antrieb aus.

WISSEN